Mandatory single-shaft concrete mixer operating procedures

a. First check whether the rotating part and the barrel are scratched before starting. If there is scratch, it should be adjusted in time.

b. The gearbox should be used after the oil is injected. The unloading worm gear and the sliding bearing should also be injected with oil.

c. Clean the material in the barrel, lock the barrel limit device, and then start the machine. If the running direction is not met after the start, the power should be cut off in time to swap any two phase lines of the wire. And restart.

d. Put the concrete mixture into the barrel, close the tube cover, and adjust the timing of the time relay according to the mixing time (must be adjusted in case of power failure).

e. Press the start button, the spindle will drive the mixer to run, and automatically stop after the set time.

f. The single-shaft forced concrete mixer stops first when unloading, then the material position limit is released by the handle, and then the hand wheel is rotated. The worm wheel rotates the barrel to the position where the discharge is convenient, stops the rotation, and then starts the machine. When the spindle is running, the material can be discharged until the material is drained to stop the spindle operation, and the hand wheel is rotated to reset the material cylinder.

g. Clean the barrel and put the water into the barrel to make the spindle run. Clean the residual material in the barrel or wash it with sand.